A shutdown team may hire four lights, a fan and a distribution kit as separate items. At the workface those items form one electrical system. A simple schedule gives the appointed electrical team a way to review the system before a vehicle leaves the equipment yard.
List loads and map the supply path
Create one line per device with its supply voltage, input rating, connector and intended operating location. Add any start-up demand, intermittent use or simultaneous operation the electrical designer needs to verify. On the sketch, show where the supply starts and where transformers, splitters and reels connect. Mark the classified boundary and the locations of plugs or connectors.
Review the components as an assembly
A splitter provides connection points. Its rating and available upstream capacity still govern the loads that can operate simultaneously. Include the cable length and routing so the electrical team can assess voltage drop, protection and earthing. Check the reel’s instructions for loading when wound or unwound, and protect the route from damage or obstruction.
Check the combination before dispatch
Daly lists the SA Equip SA POWERNET EX splitter, a SA POWERNET EX transformer and an Ex extension reel. Review each item’s configuration and suitability against the approved schedule. Make the verified wiring arrangement and equipment list available for handover so substitutions can be checked before the setup changes.
Contact Daly Middle East to discuss your project requirements.